Road Works - City of Melville 2025-2026

Find out about current road works across the City, including new roads, road widening, resurfacing, sweeping, crack sealing, footpaths, signage and stormwater works.

If you have general enquiries regarding road works, please contact our customer relations team. For enquiries relating to specific works, please contact the relevant responsible officer listed below via our customer relations team.

Civil Construction 2026-2027

   The Civil Construction Program involves delivering infrastructure improvements and construction works to enhance community facilities, road networks and public spaces.

Responsible officer: Civil Construction Supervisor.

LocationDescriptionProject Status Update
Goolugatup Lower Lands Car Park

Construction of a new car park at Goolugatup Lower Lands began in the week starting Monday, 16 March 2026. The project is expected to take several weeks to complete, with works carefully staged to minimise disruption and accommodate scheduled community events within the precinct.

Asphalt surfacing is scheduled from Wednesday, 18 November 2026, to Friday, 20 November 2026.

North Lake Road & Winterfold Road Signalised Intersection

Road safety improvements commenced Monday, 24 August 2026 at North Lake Road and Winterfold Road, including the installation of new traffic signals to improve vehicle and pedestrian safety. The works are expected to take three months to complete and are fully funded through the National Black Spot Program.

Traffic signal conduit installation is currently in progress.

Kerbing works are scheduled to commence on Tuesday, 3 November 2026.

Road Resurfacing Program 2025-2026

The Road Resurfacing Program involves repairing and renewing road surfaces to improve road safety, driving conditions and overall road quality.

Responsible officer: Road Resurfacing Program Supervisor.

LocationDescriptionProject Status Update
Murray Road, BictonThis project involves profiling works and the installation of new asphalt.
Awaiting installation of signage and pavement markings by Main Roads WA.
McCoy Street and Pitt Way, BooragoonThis project involves profiling works and the installation of new asphalt.
Awaiting installation of signage and pavement markings by Main Roads WA.


Road Renewal Program 2026-2027

Planning is currently underway for the delivery of the 2026–2027 Road Resurfacing Program. 
Initial civil upgrade works will generally be undertaken in the order listed below, with final schedules to be confirmed.

Responsible officer: Road Resurfacing Program Supervisor.

LocationCivil Works Progress & Schedule
Asphalt Works Schedule
Doney Street (North Lake Road to Norma Road), Alfred Cove
Works completed.

February 2027.

Coverley Street, Alfred CoveWorks completed.

February 2027.

Morriett Street (Kingsall Road to Stoneham Road), Attadale
Works completed.February 2027.
Mullings Way (Fenton Place to Cottrill Street), Myaree
Works scheduled between Friday, 2 October 2026 to Thursday, 15 October 2026.
March 2027.
Cottrill Street (Kitchener Road to Stammers Place), Myaree
Works scheduled between Friday, 2 October 2026 to Thursday, 15 October 2026.
March 2027.
McCoy Street (North Lake Road to Norma Road), Myaree
Works scheduled between Monday, 26 October 2026 to Thursday, 29 October 2026.
January 2027.
Sicklemoore Street (Aldridge Road to Canning Road), Booragoon
Works scheduled between Tuesday, 29 September 2026 to Thursday, 1 October 2026.February 2027.
Gunbower Street (St Michael Terrace to Reynolds Road), Mount Pleasant
Works scheduled between Monday, 2 November 2026 to Friday, 6 November 2026.
January 2027.
Hammad Street (McKimmie Road to Weld Road), Palmyra
Works scheduled between Tuesday, 29 September 2026 to Wednesday, 7 October 2026.
January 2027.
Harris Street (Hammad Street to Canning Highway), Palmyra
Works scheduled between Thursday, 1 October 2026 to Friday, 9 October 2026.January 2027.
Coogee Road (Simpson Street to Reynolds Road), Mount Pleasant
Works scheduled between Monday, 9 November 2026 to Wednesday, 18 November 2026.
November 2026.
Cleopatra Street (Petra Street to Carrington Street), Palmyra
Works scheduled between Monday, 12 October 2026 to Wednesday, 28 October 2026.
March 2027.
Roberts Road (Burke Drive to Moreing Road), Attadale
Works scheduled between Thursday, 7 January 2027 to Monday, 25 January 2027.
January 2027.
Aurelian Street (Stock Road to Justinian Street), Palmyra
Works scheduled between Wednesday, 21 October 2026 to Friday, 30 October 2026.
March 2027.
Waddell Road (Preston Point Road to 129 Waddell Road), Attadale
Works scheduled between Monday, 2 November 2026 to Wednesday, 25 November 2026.
February 2027.
Kearns Crescent (Canning Highway to Canning Highway), Ardross
To be confirmed.
January 2027.
Ogilvie Road (Kavanagh Street to Cul-de-sac), Mount Pleasant
Works scheduled between Friday, 16 October 2026 to Thursday, 22 October 2026.
March 2027.
Earnshaw Loop (Dixey Court, Eager Corner, Emery Court, Handley Court, Howlett Place, Keir Close), Leeming
Works scheduled between Friday, 12 February 2027 and Thursday, 18 February 2027.
April 2027.
Beresford Place (Gowther Street to Irwin Street), Leeming
Works scheduled between Tuesday, 9 February 2027 to Monday, 15 February 2027.April 2027.
Hewison Street (Beresford Place to Matthew Avenue), Leeming
Works scheduled between Thursday, 25 March 2027 to Wednesday, 7 April 2027.
April 2027.
Wethered Street (Bruce Court to Garvier Street), Leeming
Works scheduled between Thursday, 8 April 2027 and Wednesday, 21 April 2027.
April 2027.

Road Rehabilitation Program 2025-2026

When a road surface condition becomes poor or defective, rehabilitation or resurfacing work is needed to restore the pavement surface to the required level of service.

Responsible officer: Senior Project Engineer. 

LocationDescriptionProject Status Update
Park Road, Mount PleasantCivil upgrades and asphalt surfacing between Coogee Road and Bateman Road.

Civil and asphalt works were completed on Wednesday, 25 March 2026. 

Line marking to be completed by Main Roads WA.


Road Crack Sealing 2026-2027

Crack sealing works are undertaken to prevent water from entering the pavement through existing cracks, helping to minimise further deterioration and extend the service life of the road.

Responsible officer: Technical Officer Works Services.

LocationProject Status Update
Kintail Road, Applecross
(Forbes Road to Canning Highway, Applecross)

Works scheduled for Wednesday, 14 October 2026, and Thursday, 15 October 2026, have been postponed due to unsuitable weather conditions.

The works will be rescheduled, with new dates to be confirmed.

Parry Avenue, Bull Creek
(Karel Avenue to Rockett Way, Bull Creek)

The works are yet to be scheduled.

Electra Street, Bateman
(Leach Highway to Gannett Street, Bateman)
Quotations have been requested from contractors and are currently awaited.
Gannett Street, Bateman
(Dean Road to Electra Street, Bateman)
Quotations have been requested from contractors and are currently awaited.
Petra Street, Palmyra
(Marmion Street to Canning Highway, Palmyra)
Quotations have been requested from contractors and are currently awaited.
Petra Street, Bicton
(from Canning Highway to Preston Point Road, and from Preston Point Road to the end of Petra Street, Bicton)
Quotations have been requested from contractors and are currently awaited.


Metropolitan Regional Road Funding (MRRG) Projects 2026-2027

When a road surface condition becomes poor or defective, rehabilitation or resurfacing work is needed to restore the pavement surface to the required level of service.

Responsible officer: Senior Project Engineer. 

LocationProject Status Update
Karel Avenue (Southbound) – Beasley Road to Farrington Road, Leeming

Joint MRWA funding secured to enable pavement rehabilitation works.

Marmion Street (Eastbound & Westbound) – Justinian Street to Baal Street, Palmyra

Joint MRWA funding secured to enable pavement rehabilitation works.

Marmion Street (Eastbound) – Petra Street to Carrington Street, Palmyra

Joint MRWA funding secured to enable pavement rehabilitation works.

Riseley Street (Southbound) – Willcock Street to Drew Road, Booragoon

Joint MRWA funding secured to enable pavement rehabilitation works.

Winterfold Road (Eastbound) – Anglesey Drive to North Lake Road, Kardinya

Joint MRWA funding secured to enable pavement rehabilitation works.


Footpath Program 2026-2027

When a road surface condition becomes poor or defective, rehabilitation or resurfacing work is needed to restore the pavement surface to the required level of service.

Responsible Officer : Technical Officer Capital Works.

LocationCommentsProject Status Update
Riseley Street, ArdrossThis project involves footpath renewal works along Riseley Street, Ardross, between property numbers 48 and 62.
Footpath works have been completed. Minor brick paving infill works remain outstanding.
Woodhams Street, Willagee

This project involves the construction of a new footpath along the southern side of Woodhams Street, between Harrod Street and Wheyland Street, aligned with the kerb.

Works are scheduled to commence on Monday, 2 November 2026, and are expected to be completed within (3) three weeks.


Bus Stop / Shelter Upgrades 2026-2027

Bus shelter upgrades involve improving existing bus stop facilities, including upgrading hardstands, installing new shelters and repairing damaged shelter components to enhance passenger safety, comfort and accessibility.

Responsible Officer : Technical Officer Works Services.

NumberLocationSuburbCommentsProject Status Update
10708Marmion Street before Hornsby Street
Melville
Upgrade the hardstand and install new bus shelter.

Hardstand has been upgraded. Installation of new bus shelter has been completed.

11129
Riseley Street before Kearns Crescent
Ardross
Upgrade the hardstand and install new bus shelter.

Scheduled to be completed by the end of October 2026.

11193
Parry Avenue after Wheatley Drive
Bull Creek
Upgrade the hardstand and install new bus shelter.

Hardstand has been upgraded. Installation of new bus shelter has been completed.

26391South Street before Pinetree Gully Road
WillettonUpgrade the hardstand and install new bus shelter.
Works completed.


Road Sweeping

The City’s level of service for street sweeping is to sweep all City roads (excluding carparks) four times annually. This equates to once every 3 months and is subject to a number of factors, i.e. weather conditions, mechanical maintenance, breakdowns and operator illness etc....

Responsible Officer: Lead - Civil Maintenance.


In House Sweeper 1

Leeming
In House Sweeper 2
Attadale
Car Park SweeperOn Schedule

Drainage Capital Works 2026-2027

Drainage works involve the installation and improvement of drainage systems to manage stormwater runoff, reduce flooding risks and ensure effective water flow.

Responsible Officer: Project Engineering.

Pipe Relining Works 2026-2027

Pipe relining involves rehabilitating existing drainage pipes to improve their condition without replacing the entire pipe.

LocationProject Status Update
Corbett Way, BooragoonAll remaining Pipe Relining Works from 2025-2026 were completed in July 2026.
Parry Avenue, BatemanAll remaining Pipe Relining Works from 2025-2026 were completed in July 2026.
Reynolds Road, BooragoonAll remaining Pipe Relining Works from 2025-2026 were completed in July 2026.

Mottley Street and Warragoon Crescent, Booragoon

All remaining Pipe Relining Works from 2025-2026 were completed in July 2026.

Tanson Way, Bicton

All remaining Pipe Relining Works from 2025-2026 were completed in July 2026.

Pipe Replacement Works 2026 - 2027

The pipe replacement works involve replacing pipes that are in poor condition and are unsuitable for relining.

LocationProject Status Update

Killian Road and Canning Beach Road, Applecross

Still in planning phase due to Water Corp asset in the vicinity. Work will be scheduled soon.
Point Walter Road and Beach Street, Bicton
Still in planning phase due to Water Corp asset in the vicinity. Work will be scheduled soon.

Drainage Infiltration Works 2026 - 2027

This program involves the installation of Gully Side entry pits, soak wells and perforated pipes to reduce flooding and kerbside.

LocationProject Status Update

MacKenzie Road and Glenelg Street, Applecross

The works will commence on Monday, 16 November 2026 and expected to take 10 working days for completion.
Kishorn Road and Reynolds Road, ApplecrossContractor will plan and schedule the works in January 2027.
Davy Street and Clydesdale Street, Alfred CoveContractor will plan and schedule the works.
Davy Street and Coverley Street, Alfred CoveContractor will plan and schedule the works.
Davy Street
(Clydesdale Street to Chesson Street), Alfred Cove
Contractor will plan and schedule the works.
Davy Street (Coverley Street to Goodhew Street), Alfred CoveContractor will plan and schedule the works.

Stormwater Drainage Pit and Grate Upgrade Program 2026 - 2027

The Stormwater Drainage Pit and Grate Upgrade (Gully Renewal Program) involves upgrading and replacing drainage pits, lids, frames and grates across the City of Melville to maintain safe and effective stormwater drainage.

LocationProject Status Update

Civic Centre Car Park
(Davy Street), Booragoon

Works were completed on Friday, 9 October 2026.
14 Farrin Street, AttadaleWorks were completed on Wednesday, 7 October 2026.
Kintail Road (adjacent 914 Canning Highway), ApplecrossWorks were completed on Friday, 9 October 2026.
Bull Creek Tennis Club (4 Costello Place), Bull CreekWorks were completed on Monday, 12 October 2026.
90 Elvira Street 
(Justinian Street frontage), Palmyra
Purchase order issued and the works have been scheduled.
198 Kitchener Road, BooragoonQuotations will be received by Thursday, 5 November 2026.
203 Kitchener Road, BooragoonQuotations will be received by Thursday, 5 November 2026.
51 Potts Street, MelvilleQuotations have been invited.


Street Sign Replacement Program 2026-2027

The Street Sign Replacement Program provides for the planned renewal of street name signs and parking control signs across the City, with at least one suburb targeted for replacement each year.

Signs are renewed to ensure they remain legible, serviceable and fit for purpose.

Responsible Officer: Verge Infrastructure Supervisor.

Target SuburbProject Status Update
Leeming32% of signs have been renewed.

The replacement program is ongoing, with works progressing as scheduled.

Civil Assets Maintenance

Stormwater pit cleaning involves removing debris, sediment and other obstructions from stormwater pits to maintain proper drainage and prevent blockages and flooding

Responsible Officer: Lead - Civil Maintenance.

Stormwater Pit Cleaning

Responsible Officer: Lead - Civil Maintenance.

Please contact us during business hours if you have any questions.

Current SuburbPits cleaned
Attadale

As of July 2026, 371 pits have been cleaned to date.

Sump Fence Upgrades 2026-2027

Responsible Officer: Technical Officer - Works Services.

Please contact us during business hours if you have any questions.

LocationCommentsProject Status Update
80 Elvira Street, PalmyraThe City of Melville is installing new 1.8m high slim wall sump fencing.

Works include removing the existing fencing, replacing it with 1.8m high slim wall fencing, and installing a double gate. 

Mural artwork is planned as the next stage.

Fencing works completed.

Mural artwork in planning stage.

3 Antill Street, WillageeThe City of Melville is installing new 1.8m high slim wall sump fencing. 

Works include removing the existing fencing, replacing it with 1.8m high slim wall fencing, and installing a double gate.

Mural artwork is planned as the next stage.

Fencing works completed.

Mural artwork in planning stage.

3 Greig Street, WillageeThe City of Melville is installing new 1.8m high slim wall sump fencing.

Works include removing the existing fencing, replacing it with 1.8m-high slim wall fencing, and installing a double gate.

Mural artwork is planned as the next stage.

Fencing works completed.

Mural artwork in planning stage.

71 Adrian Street, Palmyra

The City of Melville is installing new 1.8m high slim wall sump fencing. 

Works include removing the existing fencing, replacing it with 1.8m-high slim wall fencing, and installing a double gate.

Mural artwork is planned as the next stage.

Fencing works completed.

Mural artwork in planning stage.

21 Third Street, BictonThe City of Melville is installing new 1.8m high slim wall sump fencing.

The works include removing the existing fencing, installing the new fencing and fitting a double gate. Mural artwork is planned for the next stage of the project.

Quotations have been requested and are currently awaited.