Civil Construction 2025-2026
Responsible officer: Civil Construction Supervisor.
| Location | Description | Project Status Update |
|---|---|---|
| Blue Gum Car Park Rehabilitation | The City will be rehabilitating the car park at the Blue Gum Recreation Centre, following the completion of building refurbishment works. The works will involve pavement repair, replacement of kerbs, renewal of footpaths, and asphalt resurfacing to the entire car park at the end of the project. Works will be undertaken in a staged manner to manage car park demand. The works are expected to take 6–8 weeks to complete. | Project completed. Tree planting will commence in June 2026. |
| Mitchell Street Traffic Calming | The City will be installing two traffic-calming devices on Mitchell Street, adjacent to Shirley Strickland Reserve, to help reduce vehicle speeds and improve pedestrian safety. | Asphalt works were completed on Friday, 28 November 2025. Installation of signs and pavement markings by Main Roads WA is now pending. |
| Preston Point Road & Point Walter Road – National Black Spot Project | The City has successfully secured National Black Spot funding to upgrade the intersection of Preston Point Road and Point Walter Road. To improve road safety at the intersection, the City will be installing speed control devices on the approaches to the roundabout. Works are expected to take two weeks to complete. | The asphalt and civil works have been completed. The installation of signs and pavement markings by Main Roads WA is now pending. |
| Preston Point Road & Stock Road – State Black Spot Project Stage 2 | The City has successfully secured State Black Spot funding to upgrade the intersection of Preston Point Road and Stock Road. The improvements will involve the installation of raised speed control devices on three intersection approaches to reduce speed and enhance road safety. | Asphalt works are scheduled for Wednesday, 21 January 2026. |
Road Resurfacing Program 2025-2026
Responsible officer:Road Resurfacing Program Supervisor.
| Location | Description | Project Status Update |
|---|---|---|
| Daniel Street, Attadale | This project consists of minor civil works and laying new asphalt. | Civil works were completed. Asphalt works are scheduled for January 2026. |
| Ormond Road, Attadale | This project consists of minor civil works and laying new asphalt. | Civil works were completed. Asphalt works are scheduled for January 2026. |
| Studley Road, Attadale | This project consists of minor civil works and laying new asphalt. | Civil works were completed. Asphalt works are scheduled for January 2026. |
| Tanson Road, Attadale | This project consists of minor civil works and laying new asphalt. | Civil works completed. Asphalt works are scheduled for January 2026. |
| Luff Crescent, Attadale | This project consists of minor civil works and laying new asphalt. | Civil works completed. Asphalt works are scheduled for January 2026. |
| Kitchener Road, Alfred Cove | This project consists of minor civil works and laying new asphalt. | Civil works completed. Asphalt works are scheduled for January 2026. |
| Nolan Way, Preedy Court & Mottee Road, Bateman | This project consists of minor civil works and laying new asphalt. | Civil and asphalt works have been completed. Line marking installation will be completed by Main Roads WA. |
| View Terrace, Bicton | This project consists of minor civil works and laying new asphalt. | Civil works commenced. |
| Birdwood Circus East, Bicton | This project involves minor civil works and the laying of new asphalt. | Civil works commenced. |
| Flinders Crescent, Bull Creek | This project involves minor civil works and the laying of new asphalt. | Civil works commenced. Asphalt surfacing has been rescheduled and is expected to take place mid-February 2026. |
| Windich Road, Bull Creek | This project involves minor civil works and the laying of new asphalt. | Civil works are scheduled to commence on Monday, 6 January 2026. |
Road Rehabilitation Program 2025-2026
When a road surface condition becomes poor or defective, rehabilitation or resurfacing work is needed to restore the pavement surface to the required level of service.
Responsible officer: Senior Project Engineer.
| Location | Description | Project Status Update |
|---|---|---|
| Glenelg Street, Applecross | This project consists of profiling and laying new asphalt. | Profiling works are scheduled for Tuesday, 13 January 2026. Asphalt works are scheduled for Thursday, 15 January 2026 and Friday, 16 January 2026. |
| Macrea Road, Applecross | This project consists of profiling and laying new asphalt. | Profiling works are scheduled for Tuesday, 13 January 2026. Asphalt works are scheduled for Thursday, 15 January 2026 and Friday, 16 January 2026. |
| Canning Highway, Applecross | This project consists of profiling and laying new asphalt. | Profiling works are scheduled for Tuesday, 13 January 2026. Asphalt works are scheduled for Thursday, 15 January 2026 and Friday, 16 January 2026. |
| Kintail Road, Applecross | Rehabilitation works are currently underway between Kintail Road and Kinloch Road. | Profiling works are scheduled for Tuesday, 13 January 2026. Asphalt works are scheduled for Thursday, 15 January 2026 and Friday, 16 January 2026. |
| Cromer Road, Brentwood | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for 14–19 January 2026. |
| Disney Street, Brentwood | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for 14–19 January 2026. |
| Dawson Road, Brentwood | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for 14–19 January 2026. |
| Polglass Way, Ardross | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for Friday, 16 January 2026 and Tuesday, 20 January 2026. |
| Park Road, Mount Pleasant | This project consists of civil works upgrades and laying new asphalt. | Civil works are scheduled for February 2026. Asphalt works are scheduled for March 2026. |
| Hesford Avenue, Mount Pleasant | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for March 2026. |
| Parkside Avenue, Mount Pleasant | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for March 2026. |
| Regent Avenue, Mount Pleasant | This project consists of civil works upgrades and laying new asphalt. | Civil works have been completed. Asphalt works are scheduled for March 2026. |
Roundabout Rehabilitation Works 2025-2026
Responsible Officer: Road Resurfacing Program Supervisor.
| Location | Comments | Project Status Update |
|---|---|---|
| Davy Street (rear shop entry), Booragoon | This project involves replacing kerb and infill panels. | Works are in progress. |
Metropolitan Regional Road Funding (MRRG) 2025-2026
Responsible Officer: Senior Project Engineer. Please contact us during business hours if you have any questions.
| Location | Comments | Project Status Update |
|---|---|---|
| Norma Road, Alfred Cove | This project consists of civil works including kerb renewal and a two-layer asphalt treatment on Norma Road between Canning Highway and Davy Street. | Works completed. Awaiting installation of pavement markings by Main Roads WA. |
| Murdoch Drive, Murdoch | This project consists of profiling and renewal of the asphalt wearing course, comprising a two-layer asphalt treatment on both carriageways of Murdoch Drive between Barry Marshall Parade and Bramantii Road, Murdoch. The works are extensive and will be carried out over eighteen night shifts. | Night works commenced Friday, 24 November 2025, and are scheduled for completion Tuesday, 16 December 2025. Southbound carriageway resurfacing was completed on Tuesday, 2 December 2025. Northbound carriageway resurfacing is scheduled to commence Wednesday, 3 December 2025. |
Footpath Program 2025-2026
Responsible Officer (Footpaths): Civil Assets Maintenance Supervisor.
| Location | Comments | Project Status Update |
|---|---|---|
| Davidson Road, Attadale | This project involves the renewal of footpaths and kerb replacement between Galloway and Money Road. | Works completed. |
| Rogerson Road, Mount Pleasant | This project involves the construction of a new 1.8m wide footpath, kerb replacement, new pram ramps, and associated works. | Works are scheduled to commence on Monday, 2 February 2026. |
Bus Shelter Upgrades 2025-2026
Responsible Officer: Technical Officer - Works Services. Please contact us during business hours if you have any questions.
| Number | Location | Suburb | Comments | Project Status Update |
|---|---|---|---|---|
| 10827 | Leach Highway after Joiner Street. | Melville | Shelter mesh replacement. | Works completed. |
| 11213 | Parry Avenue before Sanderson Road. | Bull Creek | The mural artwork and anti-graffiti coating have been completed. | Works completed. |
| 25894 | Canning Highway after Gairloch Street. | Applecross | Fixing the side panel mesh. | Works completed. |
Road Sweeping
Responsible Officer: Civil Assets Maintenance Supervisor.
The City’s level of service for street sweeping is to sweep all City roads (excluding carparks) four times annually. This equates to once every 3 months and is subject to a number of factors, i.e. weather conditions, mechanical maintenance, breakdowns and operator illness etc....
| In House Sweeper 1 | Leeming |
| In House Sweeper 2 | Palmyra |
| Contract Sweeping | Applecross |
| Car Park Sweeper | On Schedule |
Signs Replacement Program 2025-2026
Responsible Officer: Verge Infrastructure Supervisor.
| Project | Comments | Project Status Update |
|---|---|---|
| Bull Creek Signage Replacement Program | 59% completed. |
Drainage Works 2025-2026
Responsible Officer: Project Engineering
| Pipe relining works 2025–2026 | ||||
|---|---|---|---|---|
| Project | Location | Pipe ID | Commenced | Project Status Update |
| Pipe Relining – Remaining Projects for 2025–2026 | 61 Worragon Crescent, Attadale | 202100105992 | To be confirmed. | Relining materials have been ordered. The work schedule will be finalised with the contractor on Thursday, 22 January 2026. |
| 22 Tanson Street, Attadale | 202100105876 | To be confirmed. | Works scheduled as part of the 2025–2026 drainage program. Further updates to be provided once dates are confirmed. | |
| Corner of Mottley Street & Worragon Crescent, Attadale | 202100105938 | To be confirmed. | Project planning underway. Construction dates will be advised prior to commencement. | |
| Near 22 Parry Ave and in Harry Buckley Park, Bateman | Harry Buckley Park, Bateman | 202100112025 | To be confirmed. | Two 600mm diameter pipes have been investigated and are ready for material ordering for relining. The third pipe, 300mm in diameter, has also been investigated, and the material for its relining will be ordered soon. |
| Across Parry Avenue, outside No. 22, Bateman | 202100112059 | To be confirmed. | ||
| Harry Buckley Park, Bateman | 202100112026 | To be confirmed. | ||
| Project | Location | Commenced | Project Status Update |
|---|---|---|---|
| Pipe replacement works (unable to reline) | Corner of Killilan Road and Canning Beach Road, Applecross | To be confirmed. | Site investigation in progress. |
| Point Walter Road and Beach Road, Bicton | To be confirmed. | Site investigation in progress. | |
| Supply and Install Gully and Infiltration Systems | 18C Ullapool Road, Mount Pleasant (near Wren Street and Bombard Street) | To be confirmed. | Concept designs, estimates and scope of works have been finalised. A quote will be received following a site meeting held on Tuesday, 13 January 2026. |
| Ogilvie Road near Kavanagh Street, Mount Pleasant | To be confirmed. | Concept designs and scope of works have been completed. An estimate is being prepared and a quote will be obtained shortly. | |
| Stormwater drainage - upgrade/renewal of pit frames, lids and gully grates | Various sites | To be confirmed. | Upgrades have been completed at several sites and works will continue. |
| Winthrop | To be confirmed. | Upgrades will be carried out at 37 locations. Works are scheduled to commence in early February 2026 and are expected to take approximately three weeks to complete. |
Civil Assets Maintenance
Responsible Officer: Civil Assets Maintenance Supervisor.
Stormwater Pit Cleaning
Responsible Officer: Civil Assets Maintenance Supervisor. Please contact us during business hours if you have any questions.
| Current Suburb | Pits cleaned |
|---|---|
| Applecross |
|
Sump Fence Upgrades 2024-2025
Responsible Officer: Technical Officer - Works Services. Please contact us during business hours if you have any questions.
| Location | Comments | Project Status Update |
|---|---|---|
| 286 Marmion Street, Melville | The City of Melville is proposing to install new 1.8m high slim wall sump fencing at 286 Marmion Street, Melville. The project includes removing the existing sump fencing, replacing it with 1.8m high slim wall fencing and installing a double gate. Mural artwork is planned as the next stage of the project. | Fencing works completed on Friday, 17 October 2025. Mural artwork is planning to start in mid-January 2026. |
| 119 Matheson Road, Applecross | The City of Melville is proposing to install new 1.8m high slim wall sump fencing at 119 Matheson Road, Applecross. The project includes removing the existing sump fencing, replacing it with 1.8m high slim wall fencing and installing a double gate. Mural artwork is planned as the next stage of the project. | Fencing works were completed on Friday, 24 October 2025. The mural artwork has been completed. The anti-graffiti coating is scheduled. |
| 28 Thurso Road, Myaree | The City of Melville is proposing to install new 1.8m high slim wall sump fencing at 28 Thurso Road, Myaree. This project includes removing the existing sump fencing and replacing it with 1.8m high slim wall fencing, along with the installation of a double gate. Mural artwork is planned as the next stage of the project. | Contractor has ordered the materials and is awaiting their arrival. |
| 601 Leach Highway, Bateman | The City of Melville is proposing to install new 1.8m high slim wall sump fencing at 601 Leach Highway, Bateman. This project includes removing the existing sump fencing, replacing it with 1.8m high slim wall fencing and installing a double gate. Mural artwork is planned as the next stage of the project. | Contractor has ordered the materials and is awaiting their arrival. |