Road Works - City of Melville 2018-19

Find out about current road works across the City, including new roads, road widening, resurfacing, sweeping, crack sealing, footpaths, signage and stormwater works.

If you have general enquiries regarding road works, please call 9364 0666. For enquiries relating to specific works, please contact the relevant responsible officer listed below. 

Civil Construction Road Works

The responsible officer for civil construction road works is the Construction Supervisor, Michael Powell 9364 0728.

LocationDescriptionStatus

Murdoch Drive / Hawke Pass, Bateman

New Roundabout Construction

Works to construct a new roundabout at the intersection of Murdoch Drive and Hawke Pass are now complete.

 

Installation of pavement markings completed and awaiting installation of permanent signs is complete and awaiting final landscaping.

 

 

Murdoch Path Shared Path Stage 2C

Works to continue the construction of the Murdoch Drive Shared path resumed 18 February. Path construction will continue along Murdoch Drive from Bert Jeffrey Park towards Somerville Boulevard.

Installation of pavement markings is complete.

 

Murdoch Path Shared Path Stage 2D

Works to construct the final leg of the shared path commenced 9 April. Path construction will continue along Murdoch Drive from Bert Jeffery Park towards South Street.

Retaining wall construction continues. Bus Stop hardstand modifications in progress. Sound wall post reinstatement at bus stop completed.  Final limestone blockwork in progress.

Road Resurfacing

Responsible Officer: Road Resurfacing Program Supervisor, Iuliana Anton 9364 0783.

View the Road Rehabilitation Program for 2018-2019 for a full list of planned works.

LocationDescription & Status
North Lake Road Southbound, Winthrop (Leach Highway to Somerville Boulevard)

The project will consist of civil, profiling and asphalting works.

Remedial works are required and will be scheduled shortly. Pavement marking by Main Roads WA awaiting to be completed.

Canning Beach Road, Applecross

Completed. Pavement marking by MRWA awaiting to be completed.

Ardross Street, Applecross/ Mount Pleasant (Macrae Road to Coogee Road)

Completed. Pavement marking by MRWA awaiting to be completed.

Ardessie Street and Dornie Place, Ardross

Completed. Pavement marking by MRWA awaiting to be scheduled.

Leverburgh Street, Bragor Place and Lealt Place, Ardross

Completed. Pavement marking by MRWA awaiting to be scheduled.

Casserly Drive, Leeming

Completed. Pavement marking by MRWA awaiting to be completed.

Reynolds Road, Mount Pleasant (Crest Avenue to Canning Avenue)

The project will consist of civil, profiling and asphalting works.

A first stage consists of milling out the existing pavement and laying a bottom layer of asphalt. This is currently scheduled to commence early March.

The civil works will commence mid-March and include upgrades to drainage structures, kerbing, footpath and pedestrian ramps. The asphalt wearing course will be the last stage.

Completed. Antiskid treatment scheduled on 18 April for the Southbound lane before Canning Avenue roundabout. Pavement marking by MRWA to be scheduled.

Beach Street, Harris Street, Milne Court and Clive Street, Bicton

The project will consist of civil, profiling and asphalting works.

The civil works will commence mid-March and include upgrades to drainage structures, kerbing, footpath and pedestrian ramps.

Asphalt works are completed on Clive Street and Milne Street. Pavement marking by MRWA to be scheduled.

Civil works in progress on Beach Street and Harris Street. Asphalt works scheduled for the week commencing 6 May.

Beasley Road, Leeming

The project will consist of civil, profiling and asphalting works.

The civil works commenced 7 March and include upgrades to drainage structures, kerbing, footpath and pedestrian ramps.

Completed.  Pavement marking by MRWA to be scheduled.

Road Sweeping

Responsible Officer: Road Resurfacing Program Supervisor, Iuliana Anton 9364 0783

The City is currently sweeping roads in Ardross and Mt Pleasant.

Crack Sealing

Responsible Officer: Technical Officer Works Services, Iuliana Anton 9364 0783

Crack Sealing Program 2018-2019

Road sealing program has completed in Willagee.  Works commenced in Ardross and Applecross.

Verge Infrastructure

Responsible Officer: Verge Infrastructure Supervisor, Bryce Hunt 9364 0682

Footpath Works

Location Status

Footpaths - 2018 / 2019 Program

 

Footpath program is on schedule.

Whittle Court – Westbury Crescent to Birdwood Circus, Bicton.

Karoonda Park

Kintail Road/ Canning Beach Road

In progress

New path to Clubhouse

Lift and relay of paving

 

Signs

Responsible Officer: Verge Infrastructure Supervisor, Bryce Hunt 9364 0682

Current signage works:

Attadale Sign Replacement Program, 91% complete.

Civil Assets Maintenance

Responsible Officer: Civil Assets Maintenance Supervisor, Bradly Prideaux 9364 0734

Storm Water and Drainage

Responsible Officer: Civil Assets Maintenance Supervisor, Bradly Prideaux 9364 0734

Type of WorksDescription & LocationStatus  
Stormwater Pit Cleaning

Bull Creek

851 pits cleaned

  
 

Total Pits cleaned in 2018/19

3073

  
Stormwater Pipe Relining 

 

  

Address

 

Suburb

Pre Works Commenced

 

Relining  Commenced

 

Relining Completed

586 Canning Hwy / North Lake Road (intersection), Alfred Cove

Alfred Cove12 AprilIn progress 
47 Warragoon CrescentAttadale5 AprilIn progress 
79 Tweeddale RoadApplecross11 AprilIn progress 
15 Ardross StreetApplecross11 AprilIn progress 
Macrae RoadApplecross11 AprilIn progress 
7 Dunvegan RoadApplecross15 AprilIn progress 
Canna WayApplecross17 AprilIn progress 
28 Macrae RoadApplecross29 April  
Bicton BathsBicton29 April  
30 Tain StreetApplecross11 April11 April11 April
42 Macrae RoadApplecross30 April  
******** 
CCTV inspections of drainage pipesBull CreekWorks scheduled to commence late May  