$5 million upgrade for Melville Aquatic Fitness Centre
An exciting $5 million upgrade to the Melville Aquatic Fitness Centre (MAFC) in Booragoon will create a wider variety of services and improve the centre’s capacity, according to the City of Melville.
The redevelopment is expected to be finished by September 2011 and comes in response to the increased popularity of MAFC, which was visited by 447,276 people in 2006/07 and later received an estimated 660,000 people in 2009/10.
Chief Executive Officer Dr Shayne Silcox said the upgrade had arrived at the right time.
“The Melville Aquatic Fitness Centre is almost at full capacity and, as a result, the time has come to reinvest in this centre,” he said.
“The centre has a high level of passing traffic and is closely located to one of Perth’s busiest shopping centres. In fact, it is located within a five kilometre radius of 95 per cent of the City of Melville’s population.
“This initiative is about the responsible development of a community facility, which services a large and diverse group of residents.
“The changes will include a larger gymnasium, a group cycling facility, an interactive water playground, a dedicated room for wellness programs (such as yoga and pilates), expanded toilet and changing facilities, physically interactive gaming for teenagers, additional office space; and the installation of solar panel heating for the pool and building.
“What we are planning to achieve is a facility which has something to offer everyone across the City from Mums and Dads, to young children, teenagers and seniors.”
The tender for the MAFC redevelopment will be advertised shortly. People with enquiries should contact City of Melville Manager Health & Lifestyle Todd Cahoon on 9364 0809.
Melville Aquatic Fitness Centre
Melville Acquatic Upgrade
If the MAFC is 'almost at full capacity' as indicated by CoM CEO Dr Shayne Silcox, then perhaps the Council should not be making it any bigger, but instead invest those funds in facilities in other suburbs so that essential community infrastructure is spread around rather than being concentrated in one area (which increases other risks) - even if 95% of the population are within 5 km of the MAFC.
Melville Aquatic Fitness Centre
Melville Aquatic Fitness Centre
The project will have minimal impact on the operations or access to the swimming pools and certainly will not cause clubs or groups who use the pools to lose their ability to use the facilities.
Melville Aquatic Fitness Centre
Melville Aquatic Fitness Centre
Due to the upgrade most likely resulting in classes not running, will you be offering anything to members who will not be able to use the facilities during this period. For example, freezing the account during the renovation period.
Thanks.
Melville Aquatic Fitness Centre
MAFC Upgrade
Asside from the load of swimmers from clubs and vacation swim classes, the MAFC 50m pool at peak traffic times (before and after work) is bordering on dangerous. This pool is servicing a very large population and while it is kept beautifully clean, there really is a need for another 50m pool in the area.
RE: MAFC Upgrade
Thank you for also providing feedback regarding the cleanliness of the facility, the Centre strives to focus on this area and it is pleasing to hear feedback of this nature.
Melville Aquatic Centre Upgrade
redevelopment
The water playground does sound like a good idea.
MAFC upgrade
Swimming pools
Also the pressure on the 2 pools is enormous, with training, schools and others. We really need an outdoor pool for general swimming. Can this be included in the upgrade?
RE Melville Aquatic Centre
More contact and location details are available at:
http://www.melvillecity.com.au/facilities/recreation-centres/centre-facilities-opening-hours/melville-aquatic-fitness-centre/
MAFC : UPGRADE??
MAFC: Upgrade??
All Melville Aquatic Fitness Centre Foundation members will be able to access Melville Recreation Centre facilites including group fitness classes once the upgrade commences. An updated group fitness timetable is located here: http://www.melvillecity.com.au/facilities/recreation-centres/timetables/group-fitness-and-wellness/group-fitness-and-wellness-timetable-27-april-2011.pdf
This revised timetable will come into effect as of Wednesday 27 April 2011. Contractors are currently on site preparing for commencement of the major works set to commence on Wednesday 27 April.
Upgrade Schedule
In addition, the orignally plan was to conduct the upgrade in two phases. Is this still the case or is the whole upgrade now in one phase.
Thanks.
Melville Aquatic Fitness Centre